An effective site visit covers three layers: structure, infrastructure, legal. Skipping one item can double your post-handover retrofit cost.

Structure: floor load (tons/m²), clear height to truss, column spacing, ceiling load capacity for overhead cranes, drainage slope.

Infrastructure: power capacity at the main switchboard (KVA), process water and potable water supply, fire-protection system per TCVN code, internet bandwidth with redundancy, container staging area and turning radius.

Legal: construction permit and PCCC acceptance, environmental impact assessment (EIA) matching your sector, land-use purpose and remaining lease term, sublease and expansion clauses.